Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

MrRamon
MrRamon MrRamon
  • 13-04-2018
4 additional workers for 7 total workers.
if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12= 7 total workers. 7-3= 4 additional workers needed.
Answer Link
pranilraichura
pranilraichura pranilraichura
  • 08-03-2020

Answer:

4 workers

Step-by-step explanation:

Answer Link

Otras preguntas

y=-3x - 4 y= 2x + 1
The perimeter of a rectangle is 34 units. Its width W is 6.5 units. Write an equation to represent the perimeter in terms of the length L, and find the value
A rectangular bedroom floor has an area of 100 square feet and a length of 10 feet. What is the perimeter on the floor?
solve each system using substitution x=-2y=1 x=y-5
what is 66 2/3% in decimal form
For each handmade greeting card jacqui sells,she makes a profit of $0.35. In one week,she made a profit of $42. She sell the cards for $0.75 each. A. About ho
Write the equation in slope-intercept form. 2/3(6y+9)=3/5(15x-20)
I have 4 factors. Three of them 1,2 and 10. What is my fourth factor?
What is the importance of membrane structure and function in the organization of living processes within cells.
Order the ratios from least to greatest: 7:2, 12:4, 20:6, 21:14, 10:5