Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

Who was the 16th president?
How many unique triangles can be made where one angle measures 60° and another angle is an obtuse angle?
If ADE ABC in this diagram, which pair of ratios must necessarily be equal?
What was the jizya in the islamic empire?
What is an estimate of the equation 6n+3=2? Use a table
The slope of the line that goes through the points (0, 4) and (1, 2) is -1/2 .true false
Drinking during pregnancy can cause ________. a. attention deficit disorder in child b. poor academic performance in child c. birth defects in child d. all
A box is 70 cm long. Which of these is closest to the length of this box in feet? (1 inch = 2.54 cm) 0.21 foot 0.49 foot 1.64 feet 2.30 feet
What is the key building block of living tissue and ecosystems?
The slope of the line that goes through the points (0, 4) and (1, 2) is -1/2 .true false