A chef can finish a catering job in 4hr. His student can do the same job in 12hr. How long will it take them both to do the job if they work together

Respuesta :

shayy1616 shayy1616
  • 03-11-2021
12 divided by 4 equal 3
Ans:3hrs
Answer Link

Otras preguntas

George sold 18, 22, 26, 12, 25, 20, and 19 cars per month over the past seven months. He followed the steps below to determine the number of cars he needs to se
there’s literally a whole packet I have to do.
Can some one explain to me what substitution is and how to use it to solve equations?
PLEASE HELP! The water tank in the diagram is in the shape of an inverted right circular cone. The radius of its base is 16 feet, and its height is 96 feet. Wh
How does democracy ensure the well-being of the people? O A. The government is controlled by the workers. O B. Laws are created to protect civil rights. OC. The
The women are wearing white headscarves because white is a symbol of
....Help Please.......
Please help I will mark brainliest!
The following is an example of a/an: Because Ms. Morgan wants to go shopping A) independent clause/simple sentence B) Compound Sentence C) complex sentence D) d
nosotros / a mi abuela / enviar (to send) regalos / para su cumpleaños (birthday) tú / nunca / prestar / a mí / dinero mi madre / preparar / a nosotros / una ce